Basic Hydraulics Seminar- In-Person (Houston)

Join Hydro’s Bob Jennings for our one-day Basic Hydraulics seminar, held in-person at our HydroTex Deer Park facility in La Porte, TX.

Basic Hydraulics is a 1-day course on the hydraulic principles of operation for centrifugal pumps, with a focus on the correlation between centrifugal pump performance and the system head curve.

Continental breakfast and lunch will be provided.

Register Now

Contaminant-Free Environment for Critical Services

Pump Solutions for Clean Applications

Many critical pump applications require sanitization and assembly in a clean environment to prevent contaminants that could put the service at risk of combustion or affect the purity of the end product. To better meet our customers’ clean service needs, Hydro has installed a state-of-the-art clean room at our HydroTex Deer Park facility.

Hydro’s Deer Park clean room allows decontamination of refurbished pumps in a controlled environment. Cleaned components are inspected to ensure the absence of contaminants using a black light and are individually packaged after inspection. Upon decontamination of all components, the full pump is assembled in the clean room environment using stringent control procedures to ensure cleanliness of the equipment is maintained. The assembled pump is packaged in a sealed environment in preparation of delivery to the end user.

Since its inception in 2021, Deer Park’s clean room has become the facility of choice for various oxygen, nitrogen, and chlorine pump end users in the Houston and greater Gulf Coast regions. We are proud to add this new service to our pump subject matter expertise and industry-leading refurbishment standards.  With this winning combination, Hydro continues support our customers in ensuring safe and reliable pump operation while reducing their total cost of equipment ownership.

Capability in Action

An industrial gas customer providing medical-grade oxygen had been sending their O2 pumps for refurbishment to the overseas OEM, who does not have a US facility. HydroTex Deer Park repaired and decontaminated their O2 pumps in their dedicated clean room.

Being able to find a reliable, qualified supplier that was local to their facility saved the end user valuable time and ensured availability of this critical, lifesaving application.

Visit our HydroTex facility in La Porte.

Re-engineering System Reliability

A US fertilizer plant was experiencing recurring reliability problems with its horizontal multistage boiler feed pumps. The series of repeat failures motivated the owner plant to consult with a widely-known unbiased ­­­­aftermarket pump service provider. Previous experience with this company’s Texas facility gave the plant confidence that they had the capability to troubleshoot the problem and provide a solution. This type of supplier has been classified as a “CPRS”— Competent Pump Repair Shop, because their worldwide affiliates are staffed by specialists who have the fullest support of pump engineers at the company headquarters.

The aftermarket pump service provider performed a failure modes and effects analysis (FMEA) that took into consideration historical failure information and included an independent engineering analysis of the operating conditions. A review of the system history uncovered that the fertilizer plant had originally been designed with two 100% pumps. When the system was uprated, increased output requirements necessitated that both pumps operate in parallel to meet the new demand. Based on this information, the FMEA determined that the most probable failure mechanism was discharge recirculation caused by low flow operation.

Continue reading

Optimizing Reliability Through Material Upgrades

centrifugal pump test

The 14-stage boiler feedwater pump installed for testing to ensure that the performance achieves desired operating conditions.

At a combined cycle power plant, a boiler feedwater pump was experiencing problems. Dr. Gary Dyson of Hydro, Inc. and Larry White of HydroTex discuss how major cost savings were provided through engineering analysis, material upgrades and testing for validation.

A combined cycle power plant in the Pan Handle region of Texas found themselves experiencing repeated failure on one of their 14 stage boiler feedwater (BB3) pumps. The pump had recently been modified by the supplier to provide a short-term solution. This in turn reduced the mean time between failure (MTBF) of the pump, requiring continued support and further analysis.

Combined cycle plants are comprised of both gas and steam power production technologies, capable of producing up to 50% more electricity than traditional simple-cycle plants. With the ever-increasing demand for energy, this technology is becoming increasingly relevant in throughout the pump industry. As such, it is highly important that these plants operate at peak efficiency.

Originally, the stationary inserts at several locations in the pump assembly were modified in such a way that increased the likelihood of friction and galling of the stationary and rotating parts of the pump assembly. The consecutive failures experienced on site were repeatedly of the same failure mode, which strongly points toward a pump design problem.

Authored by Gary Dyson, Ares Panagoulias, Larry White, and Chris Brown.