a group of people looking at a computer

Engineering is at the Heart of Hydro Inc.’s Aftermarket Services

Hydro Inc. has a strong engineering capability and an expansive global reach in the pump industry, especially in aftermarket services. Pump Engineer had the pleasure of speaking with George Harris, Chief Executive Officer and Founder of Hydro Inc., where he discussed the company’s recent research initiatives, reliability support for customers, customized designs and the significance of upgrades and health audits.

Written by: Deirdre Morgan
Publisher: Pump Engineer / December 2016

“We were very fortunate that early in the company’s development we had the good fortune to work closely with Dr. Elemer Makay, a foremost consultant to the power generation industry and a specialist in troubleshooting multi-stage, high energy pumps”, states Harris. “Engineering combined with meticulous observation and analysis in the field were key to his troubleshooting process. As a result of his training over a twenty year period, engineering became the focus and strength of Hydro Inc.’s aftermarket services”.

According to Hydraulic Institute statistics, 85% of the critical pumps in industries, such as power, refineries and pipelines, are custom designed for the specific application intended. In order to properly rebuild, upgrade or troubleshoot these installations requires a solid aftermarket engineering capability and experience. Not only must the engineer understand pump fundamentals, but also the application and system in which the pump is being used, as well as the changes that may have occurred in plant operating conditions since the pump was originally installed.

Continue reading

Middle East Power Plant Demonstrates the Advantages of Pump Health Audits

With the help of a field evaluation, plant managers avoided unnecessary pump repairs.

Written by: Gary Dyson & Thomas Arakal
Publisher: Pumps & Systems / December 2016

 

A decade-old, 1,000-megawatt (MW) combined cycle power plant in the Middle East called an equipment repair and engineering company to conduct a pump health audit. Given the age of the plant and the fact that none of the pumps had undergone a major overhaul, plant personnel asked the engineering firm to determine which pumps should be pulled for repair at the next scheduled outage. The equipment consisted of six condensate extraction pumps and six boiler feed pumps.

Leaving the production process undisturbed, the field pump health evaluation team conducted a non-invasive pump study. Flow, pressure, vibration, power consumption, temperature and other data were collected for all the pumps in various regimes of operation. A team of engineers analyzed and compared the results of the measurements to the original design parameters. The study’s conclusions and engineering recommendations were published.

Continue reading